Under the planning laws you must indicate in the Planning Portal whether you need an approval from another government agency in addition to development consent. If your proposal needs another approval, we will deal with it as 'integrated development'.
Other approvals that may be needed include the following:
Department of Primary Industries - ss.89, 90 and 91 of the Water Management Act 2000
Waterways - s.91 of the Water Management Act 2000 (in Botany Bay, east of Captain Cook Bridge)
Heritage Council - s.58 Heritage Act 1977
Environment Protection Authority - Licences under ss. 43, 47, 48, 55 and 122 of the Protection of the Environment Operations Act 1997
Environment and Heritage - s.90 National Parks and Wildlife Act 1974
Roads and Maritime Services - s.138 Roads Act 1993
Department of Primary Industries - s. 144, 201, 205 and 219 of the Fisheries Management Act 1994.
Rural Fire Service - s.100B of the Rural Fires Act 1997.
If you are unsure whether another approval is needed, please consult the relevant agency. Similarly, if your proposal involves any of the above matters, we strongly recommend that you consult with the agency concerned before you lodge your application.
Applications for integrated development will be referred to the relevant agency to obtain their ‘general terms of approval'. These requirements will then be incorporated in the conditions of any development consent issued by council.
An extra fee (for each separate approval body) is needed for integrated development. The additional fee payable to an approval body must be paid via the NSW Planning Portal. The Portal will email you a payment link when Council refers the application to the approval body for assessment.